An overdue project entails closing the track gap between
Springfield and Eugene. Although
the primary structures, a pair of Walthers single track through truss bridges
(933-3185), have long been built, I needed to build most other parts of the
scene.
Bridge piers were high on the list. The prototype piers are fairly simple
concrete shapes. The standard SP
12:1 batter (downward slope) and 45-degree cutwater ends can be seen in the
prototype photo taken last Spring.
I considered various ways of replicating these piers. No commercial castings satisfied the
need. I settled on cutting them
out of wood blocks using my table saw and compound miter saw. After a trial run using a fir 2x4, I
settled on using poplar as the wood.
This is a close-grained wood readily available in local home
centers. A six-feet long 1x4 plank
became three pieces laminated to provide a 2-feet long 2.25 inch thick
block. The overall height and long
dimension batter was cut with the table saw. A 12:1 batter works out to about 5 degrees angle, easily set
on both saws. The compound miter
saw was set for the 5 degree batter and 45 degree cutwater ends (using both saw
angles available). Lots of careful
setup and clamping were necessary!
Progressive formation of bridge piers. Fir 2x4 trial pieces are on the
left. Laminated poplar block with
12:1 batter from table saw is next.
Completed bridge pier is on the right.
The poplar piers were filled and sanded. Multiple coats of “rattle can”
Rustoleum gray primer were used to seal the wood and provide a base color
coat. I am undecided as to whether
I will use this base color or go with a bit lighter gray shade provided by
hobby paint “concrete” colors. The
prototype photo shows lots of dark gray splotches, typical of weathered
concrete here in Western Oregon.
Moving on to the Eugene side approach, I am using a single
Micro Engineering 50-feet deck girder span. The prototype bridge uses a steel trestle affair, but I
needed to compromise to a single girder span given the available space. Note those same space considerations
led to the use of the Walthers through truss bridges rather than one
pin-connected truss (similar to the Central Valley truss, 21—1902) and much
longer curved chord truss of the Eugene span.
A “concrete” bridge abutment was built using styrene. I am very familiar with fabricating
styrene parts so this seemed the best way to capture the desired shape. The resulting abutment features a
pocket at the top for the girder to rest within. This gives way to the standard SP 12:1 batter sloping
down. I’ll add wing walls later as
the scene develops. The abutment
is fabricated for mounting to the underside of the plywood subroadbed. All of the bridge parts will remain
removable until the river scenery is formed and the river painted.
Front of Eugene bridge abutment.
Underside of Eugene bridge abutment.
In addition to painting the concrete parts, I also needed to
paint the steel bridges. I
ultimately had to unpack my airbrush and hook up the compressor. These highly useful modeling tools have
languished in packing from moving FAR too long! With the abutment fabricated and mounted and the piers
placed, the Willamette River bridge structures are coming together.
Willamette River Bridges in process.
I’ve chosen to mount the bridge track directly to the
“steel” bridges, making them “open deck.”
The prototype through trusses are open, but the approach spans are
ballasted decks. The Micro
Engineering deck girder matches the height of the Walthers through
trusses. There is not enough
clearance on the through trusses to add a ballasted deck, so I chose to keep
both them and the approach span open.
Bridge track is one of the next steps. I am using Micro Engineering bridge
track. I began by painting the
track an overall gray-brown.
Historically, my first choice would have been to use a “rattle” spray
can of Floquil Rail Tie Brown.
Unfortunately, Rutstoleum-Testors discontinuance of the Floquil paint
line this year eliminated that option.
Instead, I used a combination of a pair of Rustoleum (ironically!) spray
cans: Espresso and gray primer. I
sprayed the brown first and quickly followed with a light misting of the dark
gray primer. The mottled effect
provides a good base for further paint detail. Detail was supplied using Floquil paint pens (which I could
still obtain), using roof brown and weathered black on several ties. A Woodland Scenics “steel” paint pen
was used on the side of the rails.
The overall effect looks quite good to my eyes.
Painted and “weathered” bridge track.
Still to come is the pile trestle approach on the
Springfield side as seen in the prototype photo above. Having fabricated the bents from
styrene, I discovered I had not obtained the right size of strip for the
trestle stringers. An urgent trek
into Portland for the larger hobby shops there provided the necessary
materials. I hope to report on
completion of the track over the river next time.
No comments:
Post a Comment