With the central core of the railroad being used for test
operations, the time has come to begin the next major construction phase. Though conventional thought might begin
expanding from the existing layout, I am turning to the upper level: Cascade
Summit and Crescent Lake. These
stations will benefit from construction now while I still have full access to
the floor below. This is
particularly true of Crescent Lake which will be suspended from the ceiling.
I began the upper level construction phase at Cascade Summit
as it has relatively more conventional benchwork. I’ve described and diagramed how Cascade Summit hangs out
over the top of the layout below.
Now I can show pictures of this construction. The overhang, a form of “mushroom” layout design, resolves
the space needed for the summit wye.
It also separates operators on the two levels.
Cascade Summit benchwork high on the wall. Platform railing is in the mid-distance.
A 30-inch-high operator platform was built for the Cascade
Summit operators. This channels
operators on the main floor level into a path directly following the track at
the base level and initial mountain climb. The three feet wide platform provides ample space for
operators at Cascade Summit. The
platform to subroadbed height is 60-inches. This height maintains a platform to ceiling height of seven
feet—a design goal for those of us taller folk. Stools will be provided for operators and a platform lip
will prevent those stools from sliding off the platform.
Cascade Summit benchwork above, main level operator “tunnel”
below, and Cascade Summit operator platform under construction.
A modest but stout handrail
surrounds the operator platform.
Cascade Summit subroadbed. Roadbed for the summit wye extends into
the corner.
As illustrated in the track plan and Cascade Summit track
schematic, my Cascade Summit will go through a couple of ninety-degree
bends. One of those track bends
will form the base leg of the wye.
The Cascade Summit wye was used for turning steam locomotive helpers and
snow removal equipment. It was
unique as the tail of the wye was in a single-ended tunnel. The tunnel portal was just beyond the
wye switch.
RR-West of Cascade Summit, my mainline will sweep through
another ninety-degree bend to swoop out over the RR-East end of Eugene, hug the
wall through the pass-through under the house stairs, and head into Crescent
Lake which will be my upper level staging. You can see the roadbed hanging out over the backdrop on the
left side of the photo above.
Benchwork for RR-West Cascade Summit extends out over the
top of the RR-East end of the Eugene Depot area below.
Benchwork construction is an exciting time, as the physical
plant for the railroad begins taking shape. The upper level construction on my layout is even more
exciting as it includes features that resolved important design issues of
access without direct operator conflict for two levels of layout. Onward and upward!
Hey Bill,
ReplyDeleteWow! You aren't messing around, are you? Still amazes me the progress you have been able to achieve over the months. Starting on the upper deck from the "West" end of the layout is a good thing, as that will force you to keep motivated so you can connect the two sections for the full run. Must add that the bridges look fantastic you have been working on. Sorry I couldn't make it for the preliminary ops on the flat-lands... :)